Development Methodology of Industry



   1. Infrastructure                        


 Contour survey.

Master plan.

Geotechnical survey.

Detail design engineering .

Construction planning.

Jungle clearance.

Total station survey.

Traverse closing.

Checking of R.L

 Checking land profile as per         contour data.

 Detail survey for the L section
    & Cross section.

 Detail survey for the Culvert/
    causeway location.

 Complete layout and traverse
    closing

 Land levelling as per the
    design land profile.

 Checking the degree of
     compaction.

 Preparing temporary
    benchmark and location.

Preparing the approach road.

 Checking the line of collimation
    of road.

 Preparing temporary storm
    water drainage system.

 Preparing of the foundation pad
    or marking pad.



   3. Building Work

 Traverse closing of the plot
     area.

 Construction of compound
    wall.

 Checking traverse closing of the
    building.

 Checking the building
     co-ordinate.

 Preparing the foundation pad or
    marking pad as per the centre
    line drawing.

 Footing layout as per the centre
    line drawing.

 Preparing safety ribbon around
    the excavation area as per the
    HSE Plan.

 Footing excavation.

 Checking the soil strata as per
    the test report.

 Rubble soiling.

 Profile corrective course.

 Checking the footing
    reinforcement details and steel
    arrangement detail.

 Fixing and providing the
    reinforcement mesh.

 Check the footing centre line
    and footing typical details.

 R.C.C. Column.

 Checking the O/O, C/C, l/l, all
    architectural detail and traverse
    closing ground floor R.C.C.
    slab.

 U.G. Tank.

 Layout of the office, toilet, bath
    and WC room area as per the
    ground floor architectural
    drawing and similarly first floor.

 Construction of the staircase.


   2. Finishing Work for        Infrastructure

 Fixing of kerbs stone.

 Construction of footpath.

 Construction of Storm water
    drain.

 Construction of sewer line.

 Construction sewage treatment
    plant.

 Construction of water
    treatment plant.

 Municipal water supply.

 Construction of Concrete road.

 Street light.

 Construction of CFC.





























   4. Finishing Work for Building

Loading/ Unloading Platform.

Concrete block work.

Window work.

 Plastering 12mm and
    20mm.

 Plumbing work - ground and
    1st floor.

 Sanitary work - ground and 1st
    floor.

 Brick bat coba (Terrace floor)
    for water proofing.

Electrical work.

Flooring work.

Entrance gate.

Security cabin.


INDUSTRY PLAN DEPICTIONS



Industrial Elevations
- 15000 Sq ft - Option 1 & 2




5000 Sq ft Depictions - Option 1




5000 Sq ft Depictions - Option 2
(Ground Flr and First floor)




Industrial Elevations
- 5000 Sq ft - Option 1 & 2




15000 Sq ft Depictions - Option 1
(Ground Flr and First floor)




5000 Sq ft Depictions - Option 2
(Ground Flr and First floor)



1. Plot Building Specification & Infrastructure
A. Type -A 5000 Sq. ft (G+1)
Plot Size 60'- 9" x 82' - 6"
B. Type -B 15000 Sq. ft (G+1)
Plot Size 100' - 6" x 149' - 3"
C. Plot FSI 1
D. Construction
Ground floor 0.5
First Floor 0.5
E. Vaastu Compliance All plots are facing East-West , Vaastu Compliant
F. Plot access Access from 15 Mtrs. (49' - 3'') wide Motorable Road
G. Water Supply MIDC Equivalent Water Supply of 1000 liters
H. Power supply 10 KVA for 5000 sq. ft. plot; 30 KVA for 15000 sq. ft. plot
I. Utilities Junction Well planned Duct Trench System for Utilities (Power, Water, Sewerages, Communication, ETP, Drainage, Fire Fighting Lines)
J. Applied DCR for the plot Plot development as per development control rules of 'A' class municipality according to DCR of MMR
K. NOC for the plan NOC on the plan approved of the plot by SPV is compulsory
2. Plinth, Back Yard & surrounding Area Specification
A. Footings R.C.C. Footings, size 4'-0" x 4'-0" x 3'-0" High
B Column R.C.C. Columns ,size 1'- 3" X 1'-10" at 19' 8" x 19' 8" C/C(Grid)
C. Plinth Plinth Height = 4' - 0'' High
D Size Of Plinth A Type - 62'-10" x 39' -10", Model No. 1 (5000 sqft plot )
B Type - 114'-8" x 65' -4", Model No. 2 (15000 sqft plot)
E. Back Yard & Surrounding Area Covered With M-15 Grade concrete ,Precast 65 mm thick Paverblock (Coloured) With sand Bedding
F Compound Wall 1.8 mtr. (6 Feet ) high, 200 mm( 8") thick concrete block With 1'- 3" x 1'-3" column 16"- 4" C/C , Above ground level with R.C.C. Coping on top.
G. Main Gate / Exit Gate 6'-0" high M.S. Gate In two leaves with channel pickets, pivoted square bars including top & bottom guide rollers. vacate gate in single leaf with same standards
H. Watchman Cabin / Meter Room WatchMan Cabin & Meter Room 7 Feet High With 6" High Plinth of size 6'-6" x 6'-6"
I. Water Domestic Use - 6000 litre U.G. Tank (6'- 6" x6'- 6" x 6'- 6" size) For A -Type - 10000 litre U.G Tank ( 8'- 2" x6'- 6" x 6' -6") For B-Type
J. Septic tank For 50 users(16'- 4" x 6'- 7" x 4' -11")
3. Ground Floor Specification
A. Height Floor high 16 feet (inclusive of slab thickness), Clear Height - 15'-8"
B Slab 4" Thick R.C.C slab in M-25 grade Concrete Supported by 1'-0'' x 1'- 3" Beams @ 14' - 9" Level, & 1'-0"x1' -3" Size columns Design To Take Safe Load
C. Column R.C.C column of Size 1'-0''x1'- 3" Grid Distance 19' 8" x 19' 8"
D Flooring Industrial Flooring , I.P.S. Finishing With Tremix Machine
E Walls Block work - 200 mm (8'') thick with internal plaster 12 mm thick and sand faced plaster with 20 mm (0.8'') thick
F. Lintel / Chajja R.C.C. Lintel, R.C.C Chajja 6 " thick ,Projected 2 feet wide on Windows
G Openings Galvanised Rolling Shutters - 8' 2" x 8' 2" .
Roolling shutter G.I 18 / 19 gauge, removable Lathes interlocked with spring 1' long
H. Plumbing G.I. Pipes - 'C' class, G.I. Pipes, PVC Rainwater pipes as per I.S. Standard
4. First Floor Specification
A. Slab hight Floor high12 feet (inclusive of slab thickness), Clear Height - 11'-8"
B Slab, column, Flooring, Walls, Lintel / Chajja, Plumbing as per ground coverage
C. Openings Flush Doors 50mm (2") thick Composite Panel
D Staircase R.C.C Staircase With Waist Slab 150mm (6") Thick, 300mm (1'-0") WideTread, Riser 150mm (6") high ,Topped With Kaddapa stone of size 4'-0" x 1'-0"
5. Terrace Specification
A. Water Domestic Use - 6000 litre. Overhead Rcc Water Tank for -A type Industry 10000 litre OH Tank For B type of Industry
B Water proofing terrace Water proofing 50mm Thk terrace with marble mosaic finish
C. Parapat wall 2 feet parapat wall plastered with double coat plaster
D Ladder 8 feet long M.S ladder for O.H tank