Traverse closing of the plot area.
Construction of compound wall.
Checking traverse closing of the building.
Checking the building co-ordinate.
Preparing the foundation pad or marking pad as per the centre line drawing.
Footing layout as per the centre line drawing.
Preparing safety ribbon around the excavation area as per the HSE Plan.
Footing excavation.
Checking the soil strata as per the test report.
Rubble soiling.
Profile corrective course.
Checking the footing reinforcement details and steel arrangement detail.
Fixing and providing the reinforcement mesh.
Check the footing centre line and footing typical details.
R.C.C. Column.
Checking the O/O, C/C, l/l, all architectural detail and traverse closing ground floor R.C.C. slab.
U.G. Tank.
Layout of the office, toilet, bath and WC room area as per the ground floor architectural drawing and similarly first floor.
Construction of the staircase.
|